12. Subsequent Events |
6 Months Ended |
---|---|
Jun. 30, 2017 | |
Subsequent Events [Abstract] | |
Subsequent Events |
The Company performed a review of events subsequent to the balance sheet date through the date the financial statements were issued and determined that there were no such events requiring recognition or disclosure in the financial statements except as noted below.
On August 27, 2015, Eurogentec S.A. (“EGT”), a former supplier of the Company, brought an action against the Company in the Commercial Court of the Canton of Zurich Switzerland (the “Court”) alleging nonpayment of invoices for services provided by EGT. The Company requested dismissal of the claim based on the argument that EGT knew, or should have known, that the services provided by EGT should not have been performed or had not been properly performed. On July 12, 2017, the Court rendered a decision in favor of EGT ordering the Company to pay approximately $0.7 million to EGT, representing all amounts that EGT alleged were owed by the Company, plus interest and court and legal fees.
The Company had previously recorded $0.6 million related to this contract when the relevant costs were incurred. As a result of this ruling, the Company has accrued an additional $0.1 million related to interest and fees associated with the ruling. The Company intends to defend this action vigorously. |